Project records
Civic projects that span several wards, followed over time. Each record separates official documents, attributed reporting, conflicting figures and what could not be found.
Road widening + elevated corridor · SH-35
Delayed
Varthur–Gunjur road corridor
Work began in 2019. The latest publicly reported target is December 2026.
- Agency
- KRDCL
- Next public target
- Dec 2026
- Affected wards
- Varthur · East Ward 40 · Gunjur · East Ward 50
Open the record
Elevated flyover · Intermediate Ring Road, Koramangala
Delayed
Ejipura–Kendriya Sadan flyover
Work began in 2017 with a November 2019 deadline. The latest reported target is opening to traffic in November 2026, after an October 2026 target reported in May.
- Agency
- GBA
- Next public target
- Nov 2026
- Affected wards
- 5 wards · Central, South
Open the record
Elevated metro line · Outer Ring Road
Delayed
Namma Metro Phase 2A: Central Silk Board to KR Puram
Civil work began in mid-2021 on 30-month contracts. The opening target has moved from 2021 to about mid-2027, and trial runs from October 2026 will skip two unfinished stations.
- Agency
- BMRCL
- Next public target
- Mid-2027
- Affected wards
- 21 wards · Central, East, South
Open the record
Suburban rail corridor · Suburban Rail Corridor 2
Delayed
Bengaluru Suburban Rail Corridor 2 (Mallige Line)
L&T terminated its Corridor 2 civil contract in July 2025, and the remaining work was re-tendered. K-RIDE now targets first services by December 2028; the project deadline was separately reported as extended to March 2030.
- Agency
- K-RIDE
- Next public target
- Dec 2028
- Affected wards
- 30 wards · Central, North, West
Open the record
Access-controlled expressway · Peripheral Ring Road
Delayed
Peripheral Ring Road (Bengaluru Business Corridor)
Only Package 1 of the first phase has a contractor; in June 2026 BBCL's chairman said the work order would be issued within two days. The other first-phase packages still lack most of their land, and the second phase was final-notified only in September 2026.
- Agency
- BDA
- Next public target
- 2029
- Affected wards
- 12 wards · East, North, South
Open the record
Water supply and sewerage scheme · T.K. Halli–Vajarahalli transmission main
In progress
Cauvery Water Supply Scheme Stage V
The water-supply system was inaugurated on 16 October 2024 after several missed commissioning dates. Connection and sewerage work was still reported incomplete in 2025 and 2026.
- Agency
- BWSSB
- Next public target
- Not public
- Affected wards
- Not attached to wards
Open the record
Records also appear on the ward sheet of every affected ward, and in map search.