Ejipura–Kendriya Sadan flyover

The roughly 2.5 km flyover from Ejipura Junction to Kendriya Sadan began under BBMP in 2017 and missed its November 2019 deadline, then went through contract cancellation and repeat tenders. Reporting says the Karnataka cabinet revised the project cost to ₹307.96 crore in September 2023, while later public updates moved the completion target repeatedly. The reviewed public sources did not include the operative work order, current accepted contract value and payment schedule, or an official progress report as of the review date.

Responsible agency

GBA

Greater Bengaluru Authority (GBA), formerly BBMP

Affected current wards

5 wards · Central, SouthShow
  • Agaram · Central Ward 24
  • A Adugodi · South Ward 24
  • Sri Lakshmi Devi Ward · South Ward 27
  • Kormangala East · South Ward 28
  • Kormangala West · South Ward 29

Wards within 40 m of the flyover as mapped in OpenStreetMap (checked 17 September 2026). Kaun derived this list; the agency does not publish one.

Open accountability gap

The current work order, milestone schedule, payments and a dated official progress report were not found in the public sources reviewed.

Length

2.5 km

Reported consistently in court coverage and project reporting.

Original cost

₹203–204 Cr

Reports give both figures; the sources reviewed do not reconcile them.

Revised cost

₹307.96 Cr

The Hindu reported a cabinet revision in September 2023; the cabinet record itself was not found.

Original deadline

Nov 2019

The May 2017 work order allowed 30 months, per court reporting.

Live research desk

AI WEB SEARCH

Ask one narrow question about this project. Kaun checks its record first, then runs an AI web search. AI answers are labelled, are not reviewed, and may be shown to other visitors who ask the same question for up to seven days.

Deadline and scope trail

NEWEST FIRST
  1. Latest reported target moves to November 2026

    Transport Minister Ramalinga Reddy was reported as saying most work was complete and the flyover would open to traffic in November 2026. No later official completion report was found by the 16 September review date.

    Attributed report
  2. Completion target moves to October 2026

    GBA's chief commissioner was reported to have directed additional deployment to meet an end-October 2026 target. The update reported 731 of 762 segments cast and 52 of 66 spans completed.

    Attributed report
  3. Completion contract announced with a 15-month target

    BBMP was reported to have announced a new completion contract in November 2023 with a 15-month deadline. The operative work order and exact commencement date were not found in the public sources reviewed.

    Attributed report
  4. Cabinet reportedly revises total project cost

    The Hindu later reported that the Karnataka cabinet agreed to revise the total project cost to ₹307.96 crore in September 2023. The exact cabinet decision date and primary cabinet record were not found in the public sources reviewed.

    Attributed report
  5. Third tender attempt scrapped over price

    BBMP scrapped its third tender to complete the flyover. The lone bidder quoted ₹205 crore against an estimate of ₹144 crore, and officials said the estimate would be reviewed.

    Attributed report
  6. Court permits an undertaking for completion by December 2022

    The High Court gave the original contractor an opportunity to file an undertaking to complete the flyover by 31 December 2022. In January 2023, BBMP invited bids to complete the project.

    Attributed report
  7. State cancels the original contract

    The Urban Development Department was reported to have cancelled the contract and ordered forfeiture of a ₹10.16 crore security deposit. The report said progress stood at 42.83% and directed BBMP to retender the remainder within the ₹204 crore project cost.

    Attributed report
  8. High Court directs BBMP to lodge an FIR and act on the contract

    The High Court was reported to have directed the BBMP commissioner to lodge an FIR concerning alleged misappropriation of public funds and to take steps including contract cancellation. This entry records the court direction as reported and does not state the outcome of any investigation.

    Attributed report
  9. High Court seeks a completion timeline

    In PIL proceedings, the Karnataka High Court directed BBMP to state its timeline for completing the flyover. The petitioner said only about half the work had been completed.

    Attributed report
  10. Extended deadline also missed

    The PIL petitioner told the High Court that BBMP had extended the deadline to December 2020 after imposing a penalty for delay, and that the work was still incomplete.

    Attributed report
  11. Original completion period ran out

    The 30-month period from the May 2017 work order ran out in November 2019 without the flyover being completed.

    Attributed report
  12. Original work order issued

    Court reporting states that BBMP issued the construction work order on 4 May 2017, at a reported cost of ₹203 crore, with a 30-month delivery period.

    Attributed report

Known, contested, missing

Responsible agency

Attributed report

GBA (formerly BBMP)

BBMP procured and managed the project; 2026 updates describe directions by the GBA chief commissioner.

AS OF 2026-09-16

Contractor

Not found publicly

Not in primary records reviewed

News and court reporting names the original and replacement firms, but the evidence rules require a primary record before naming a contractor. The original and current work orders were not found in the public sources reviewed.

AS OF 2026-09-16

Accepted cost

Attributed report

₹307.96 Cr reported; current contract value unknown

A September 2023 cabinet revision to ₹307.96 crore was reported, but the primary cabinet record and current work order were not found. Other reports cite ₹176 crore for pending work, which is a different cost basis and is not treated as the total project cost.

AS OF 2023-09-01

Litigation

Attributed report

PIL W.P. 13605/2021

Court reporting identifies Adinarayan Shetty v. State of Karnataka as a PIL over delay. Reported directions included submission of a time-bound plan, action on the contract, and an opportunity for a completion undertaking.

AS OF 2022-03-29

Official progress record

Not found publicly

Not found publicly

The reviewed sources did not provide a current agency progress report with a dated physical and financial progress statement as of 16 September 2026.

AS OF 2026-09-16

Source ledger

  1. 01
  2. 02
  3. 03
    Government cancels Ejipura flyover tender

    The Hindu · 2022-03-08 · news

  4. 04
  5. 05
  6. 06
    Palike all set to resume Ejipura flyover project

    The Times of India · 2023-10-25 · news

  7. 07
  8. 08
  9. 09
    Ejipura flyover to finally open to traffic in November

    Public TV English · 2026-08-26 · news