Elevated flyover
Ejipura–Kendriya Sadan flyover
The roughly 2.5 km flyover from Ejipura Junction to Kendriya Sadan began under BBMP in 2017 and missed its November 2019 deadline, then went through contract cancellation and repeat tenders. Reporting says the Karnataka cabinet revised the project cost to ₹307.96 crore in September 2023, while later public updates moved the completion target repeatedly. The reviewed public sources did not include the operative work order, current accepted contract value and payment schedule, or an official progress report as of the review date.
Responsible agency
GBA
Greater Bengaluru Authority (GBA), formerly BBMP
Affected current wards
5 wards · Central, SouthShowHide
- Agaram · Central Ward 24
- A Adugodi · South Ward 24
- Sri Lakshmi Devi Ward · South Ward 27
- Kormangala East · South Ward 28
- Kormangala West · South Ward 29
Wards within 40 m of the flyover as mapped in OpenStreetMap (checked 17 September 2026). Kaun derived this list; the agency does not publish one.
Open accountability gap
The current work order, milestone schedule, payments and a dated official progress report were not found in the public sources reviewed.
Length
2.5 km
Reported consistently in court coverage and project reporting.
Original cost
₹203–204 Cr
Reports give both figures; the sources reviewed do not reconcile them.
Revised cost
₹307.96 Cr
The Hindu reported a cabinet revision in September 2023; the cabinet record itself was not found.
Original deadline
Nov 2019
The May 2017 work order allowed 30 months, per court reporting.