ProjectsKAUN?

Elevated metro line

Outer Ring RoadCentral Silk Board to KR Puram

Namma Metro Phase 2A: Central Silk Board to KR Puram

Phase 2A is a 19.75 km, 13-station elevated Blue Line section along the Outer Ring Road IT corridor, from Central Silk Board to KR Puram, approved by the Union Cabinet in April 2021 together with Phase 2B at ₹14,788.101 crore. Afcons Infrastructure and Shankaranarayana Constructions began civil work in mid-2021 on 30-month contracts; the opening has since moved from 2021 (2016 DPR) to about mid-2027, with October 2026 trial runs skipping the unfinished Marathahalli and Silk Board stations. Main evidence gap: no Phase-2A-specific cost, progress, or contractor delay figures are public — the sanctioned cost and the 72.75% progress both combine Phases 2A and 2B.

Responsible agency

BMRCL

Bangalore Metro Rail Corporation Limited (BMRCL)

Affected current wards

21 wards · Central, East, SouthShow
  • Kasturi Nagar · Central Ward 12
  • Krishnaiahnapalya · Central Ward 13
  • Agaram · Central Ward 24
  • Dooravaninagar · East Ward 18
  • K.S. Nissar Ahmed Ward · East Ward 19
  • A Narayanapura · East Ward 20
  • Mahadevapura · East Ward 22
  • Bharath Aikya Ward · East Ward 36
  • Munnenkolalu · East Ward 41
  • Priyadarshini Ward · East Ward 42
  • Dodda Nekkundi · East Ward 43
  • Ashwath Nagar · East Ward 44
  • Marathahalli · East Ward 45
  • Bellanduru · East Ward 47
  • Panathur · East Ward 48
  • Shivanasamudra Ward · East Ward 49
  • Viswamanava Kuvempu Ward · South Ward 18
  • Madiwala · South Ward 20
  • Jakkasandra · South Ward 30
  • Iblur · South Ward 70
  • HSR Layout · South Ward 72

Wards within 40 m of the line as mapped in OpenStreetMap (checked 17 September 2026). Kaun derived this list; the agency does not publish one.

Open accountability gap

No Phase 2A-only cost or progress figure is public. The ₹14,788 crore sanction and the 72.75% progress figure (June 2026) both combine Phases 2A and 2B.

Length

19.75 km

13 elevated stations, per BMRCL's January 2023 presentation. The 2021 sanction covers 58.19 km across Phases 2A and 2B.

Sanctioned cost (2A + 2B)

₹14,788 Cr

Union Cabinet approval, 20 April 2021. No Phase 2A-only figure is published; the 2016 DPR estimated ₹4,202 crore for this corridor.

Civil contracts

₹1,409 Cr

Afcons ₹785.23 crore (Package 1) and Shankaranarayana Constructions ₹623.55 crore (Package 2), per BMRCL's January 2023 presentation.

Progress (2A + 2B)

72.75%

As of June 2026, per the Union housing ministry's Lok Sabha reply reported by The Indian Express. No Phase 2A-only figure is published.

Live research desk

AI WEB SEARCH

Ask one narrow question about this project. Kaun checks its record first, then runs an AI web search. AI answers are labelled, are not reviewed, and may be shown to other visitors who ask the same question for up to seven days.

Deadline and scope trail

NEWEST FIRST
  1. Minister moves Phase 2A opening to mid-2027; full Blue Line by March 2028

    Greater Bengaluru Development Minister Krishna Byre Gowda said Phase 2A, which earlier had a December 2026 deadline, would likely open by mid-2027, and the full Blue Line (including Phase 2B to the airport) by March 2028. A week earlier he had indicated Phase 2A could open by March 2027.

    Attributed report
  2. Trial runs set for October 2026 but will skip two unfinished stations

    Trial runs are planned from October 2026 in two segments (KR Puram-Marathahalli and Marathahalli-HSR Layout), skipping Marathahalli and Silk Board stations where construction is unfinished; the turnback section over the BDA flyover past Silk Board is also still being built.

    Attributed report
  3. Silk Board interchange walkway contract awarded for ₹55.48 crore

    BMRCL awarded the elevated travelator/walkway linking the Blue Line and Yellow Line stations at Silk Board to Milan Road Buildtech LLP for ₹55.48 crore against an estimate of ₹58.99 crore, with nine months for completion.

    Attributed report
  4. MoHUA tells Lok Sabha Phases 2A+2B are 72.75% complete

    The Union Ministry of Housing and Urban Affairs told the Lok Sabha that Phases 2A and 2B (58.19 km) were 72.75% complete as of June 2026. BMRCL said the Silk Board-KR Puram stretch should open by late 2026. The reply does not break out Phase 2A alone.

    Attributed report
  5. BMRCL tells ORRCA the line will open only by December 2026

    At a review meeting with the Outer Ring Road Companies Association, BMRCL's managing director said the Silk Board–KR Puram line would be ready for operations by December 2026, BLR Post reported.

    Attributed report
  6. High Court disposes of acquisition writs over metro land near KR Puram

    In Royal Heritage Apartment Owners' Association vs BMRCL (WP 16862/2021 c/w WP 490/2023), the Karnataka High Court disposed by consent of challenges to KIADB acquisition notifications of 2021 for land at Benniganahalli village, KR Puram Hobli, abutting BMRCL property. The acquired area was cut from 261.28 to 119.68 sq m, the General Award of 21 Dec 2021 was quashed, and compensation of about ₹2.54 crore was agreed under Section 29(2) of the KIAD Act, with structure valuation sent to the Reference Court. The order does not state which metro phase the land was for.

    Verified record
  7. BMRCL presentation still shows 30 June 2024 expected completion for both packages

    In a presentation to the Outer Ring Road Companies Association, BMRCL listed both civil packages with expected completion on 30 June 2024, contract values ₹785.23 crore (Afcons) and ₹623.55 crore (Shankaranarayana), and the 13-station list for the 19.75 km corridor.

    Verified record
  8. High Court permits felling 577 trees, translocating 212 on Silk Board-Kadubeesanahalli stretch

    A division bench of the Karnataka High Court permitted BMRCL to remove 833 trees (577 felled, 212 translocated, 44 retained) between Central Silk Board and Kadubeesanahalli, acting on the court-appointed Technical Expert Committee's recommendation. BMRCL had applied in June 2021; a second application for 1,026 trees between Kadubeesanahalli and KR Puram was pending.

    Attributed report
  9. Civil work begins; both contracts expected complete by 30 June 2024

    BMRCL's own presentation records Package 2 starting 28 June 2021 and Package 1 starting 5 July 2021, each with an expected completion date of 30 June 2024. It also records that tree clearance permission took about 8 months and the GAIL gas line shift took 12 months from project commencement.

    Verified record
  10. Central sanction order sets five-year completion

    The Ministry of Housing and Urban Affairs issued the sanction order for the 58 km Central Silk Board-KIA line at ₹14,788.101 crore, to be completed in five years; Centre and State to fund 20% each, 60% by loans.

    Attributed report
  11. BMRCL awards two civil contracts worth about ₹1,409 crore

    Contract PHASE 2A/P1/60(a) to Afcons Infrastructure (₹785 crore, 30 months) and PHASE 2A/P2/60(b) to Shankaranarayana Constructions (₹623 crore, 30 months), covering the full 18.3-19.75 km corridor and its 13 stations.

    Attributed report
  12. Union Cabinet approves Phases 2A and 2B: 58.19 km, ₹14,788.101 crore

    The Union Cabinet approved Phase 2A (Central Silk Board Junction to KR Puram) and Phase 2B (KR Puram to the airport via Hebbal), 58.19 km in all, at a completion cost of ₹14,788.101 crore. The Hindu reported that the project would be completed in five years if all went as planned, and that land acquisition for Phase 2A was already complete.

    Verified record
  13. Financial bids opened: Afcons lowest for Package 1, Shankaranarayana for Package 2

    Afcons Infrastructure quoted ₹785.25 crore against an estimate of ₹731.18 crore for Package 1 (Silk Board-Kadubeesanahalli), and Shankaranarayana Constructions quoted ₹623.55 crore against ₹594.25 crore for Package 2 (Kodibeesanahalli-KR Puram).

    Attributed report
  14. BMRCL floats civil tenders in two packages

    BMRCL invited tenders for the roughly 19 km elevated corridor with 13 stations: Package 1 (9.85 km, 6 stations plus a 2.8 km flyover at Silk Board, estimate ₹731.2 crore) and Package 2 (9.74 km, 7 stations plus a link line to Byappanahalli depot, estimate ₹594.2 crore). A senior official said a December 2023 deadline was still possible; sources put the revised corridor estimate at about ₹5,300 crore.

    Attributed report
  15. DPR: ORR metro estimated at ₹4,202 crore, operational by 2021

    BMRCL's in-house team prepared the detailed project report for the Central Silk Board-KR Puram corridor in October 2016, estimating ₹4,202 crore and operation by 2021. A tender floated in 2018 was cancelled after the cash-strapped IL&FS emerged lowest bidder in all packages.

    Attributed report

Known, contested, missing

Responsible agency

Verified record

BMRCL

Named in the PIB release of the Union Cabinet approval and in every tender and contract record.

AS OF 2021-04-20

Contractor

Verified record

Afcons (Package 1), Shankaranarayana (Package 2)

BMRCL's January 2023 presentation names both civil contractors and their contract values. The Silk Board interchange walkway contract (Milan Road Buildtech LLP, ₹55.48 crore, August 2026) is named only in news reporting. Amounts actually paid were not found in the public sources reviewed.

AS OF 2026-08-19

Accepted cost

Verified record

₹14,788 Cr for 2A + 2B; 2A alone not published

PIB release of the April 2021 Cabinet decision. The 2016 DPR estimated ₹4,202 crore for the ORR corridor alone, and 2019 reporting cited a revised corridor estimate of about ₹5,300 crore. No revised Phase 2A estimate after 2021 was found in the public sources reviewed. The Indian Express reported a ₹40,425 crore revised cost for Phase 2 in May 2025, and discussed Phases 2A and 2B separately.

AS OF 2021-04-20

Litigation

Attributed report

No stay found

The disposed writ near KR Puram is documented in the court record on Indian Kanoon; it was resolved by consent and did not stay the project. The December 2021 tree order is documented in news reporting of the court's order. No pending stay or injunction against Phase 2A was found in the public sources reviewed.

AS OF 2023-07-14

Funding

Attributed report

ADB and JICA loans; 60% debt

Reported by The Hindu at Cabinet approval and sanction time; BMRCL's presentation confirms ADB financing of both civil packages.

AS OF 2021-06-08

Next opening target

Attributed report

Mid-2027

Minister Krishna Byre Gowda's statement of 22-23 Aug 2026; a week earlier he had indicated March 2027 for Phase 2A, so treat the month as approximate.

AS OF 2026-08-23

Source ledger

  1. 01
    Cabinet approves Bangalore Metro Rail Project Phase 2A and Phase 2B

    Press Information Bureau, Ministry of Housing & Urban Affairs · 2021-04-20 · official

  2. 02
  3. 03
  4. 04
  5. 05
  6. 06
  7. 07
  8. 08
    Bangalore Metro Rail Project - PH-2A (BMRCL presentation, 10 Jan 2023)

    BMRCL, hosted by ORRCA · 2023-01-10 · official

  9. 09
  10. 10
  11. 11
  12. 12
  13. 13
  14. 14
  15. 15