Elevated metro line
Namma Metro Phase 2A: Central Silk Board to KR Puram
Phase 2A is a 19.75 km, 13-station elevated Blue Line section along the Outer Ring Road IT corridor, from Central Silk Board to KR Puram, approved by the Union Cabinet in April 2021 together with Phase 2B at ₹14,788.101 crore. Afcons Infrastructure and Shankaranarayana Constructions began civil work in mid-2021 on 30-month contracts; the opening has since moved from 2021 (2016 DPR) to about mid-2027, with October 2026 trial runs skipping the unfinished Marathahalli and Silk Board stations. Main evidence gap: no Phase-2A-specific cost, progress, or contractor delay figures are public — the sanctioned cost and the 72.75% progress both combine Phases 2A and 2B.
Responsible agency
BMRCL
Bangalore Metro Rail Corporation Limited (BMRCL)
Affected current wards
21 wards · Central, East, SouthShowHide
- Kasturi Nagar · Central Ward 12
- Krishnaiahnapalya · Central Ward 13
- Agaram · Central Ward 24
- Dooravaninagar · East Ward 18
- K.S. Nissar Ahmed Ward · East Ward 19
- A Narayanapura · East Ward 20
- Mahadevapura · East Ward 22
- Bharath Aikya Ward · East Ward 36
- Munnenkolalu · East Ward 41
- Priyadarshini Ward · East Ward 42
- Dodda Nekkundi · East Ward 43
- Ashwath Nagar · East Ward 44
- Marathahalli · East Ward 45
- Bellanduru · East Ward 47
- Panathur · East Ward 48
- Shivanasamudra Ward · East Ward 49
- Viswamanava Kuvempu Ward · South Ward 18
- Madiwala · South Ward 20
- Jakkasandra · South Ward 30
- Iblur · South Ward 70
- HSR Layout · South Ward 72
Wards within 40 m of the line as mapped in OpenStreetMap (checked 17 September 2026). Kaun derived this list; the agency does not publish one.
Open accountability gap
No Phase 2A-only cost or progress figure is public. The ₹14,788 crore sanction and the 72.75% progress figure (June 2026) both combine Phases 2A and 2B.
Length
19.75 km
13 elevated stations, per BMRCL's January 2023 presentation. The 2021 sanction covers 58.19 km across Phases 2A and 2B.
Sanctioned cost (2A + 2B)
₹14,788 Cr
Union Cabinet approval, 20 April 2021. No Phase 2A-only figure is published; the 2016 DPR estimated ₹4,202 crore for this corridor.
Civil contracts
₹1,409 Cr
Afcons ₹785.23 crore (Package 1) and Shankaranarayana Constructions ₹623.55 crore (Package 2), per BMRCL's January 2023 presentation.
Progress (2A + 2B)
72.75%
As of June 2026, per the Union housing ministry's Lok Sabha reply reported by The Indian Express. No Phase 2A-only figure is published.